Timeline

Date

Event

7/15/2021

Submitted sketch plan review to York County

8/3/2021

Received York County comments to sketch plan review

12/9/2022

Submitted revised sketch plan application

12/13/2022

County rejected application for sketch plan review

5/23/2023

Traffic Impact Analysis (TIA) Submitted

6/30/2023

Submitted Nationwide Permit Application for site impacts

7/11/2023

Received response with comments for TIA

7/21/2023

Submitted site plan to York County and Office of School Facilities (OSF)

7/23/2023

Resubmitted TIA

7/28/2023

Received response from ACE requesting additional information

8/11/2023

Received response with comments for resubmitted TIA

8/23/2023

Received response from Department of Health and Environmental Control (DHEC) requesting additional information

8/25/2023

Submitted requested additional information to ACE

8/25/2023

Received denial from York County for site plan

9/5/2023

Submitted requested additional information to DHEC

10/12/2023

Received approval from Zoning Board of Appeals (ZBA) to waive buffer tree survey

10/16/2023

Received Daimler Blvd. encroachment permit (for school entrances)

10/16 - 20/2023

Conducted a second traffic study at W. Liberty Hill Rd. and Hwy. 274 and at Hwy. 49 and Hwy. 274

10/18/2023

Received second denial from York County for site plan