Clover High School Renovations
Task Name | Start | Finish |
---|---|---|
Fitness & Wellness Center | 10/2023 | 10/2024 |
Commons/Media Center | 11/2023 | 7/2024 |
Traffic Loops | 3/2024 | 7/2024 |
Tennis Courts | 7/2023 | 3/2024 |
Track Renovation | 11/2023 | 4/2024 |
Project Budget
Total Budget | Construction Budget | Owner Costs |
---|---|---|
$17,000,000.00 | $13,465,000.00 | $3,535,000.00 |
Tennis Courts
Completed Project