Lake Wylie High School
Project Timeline
Task | Start Date | End Date |
---|---|---|
Design & Permitting | 12/2022 | 12/2023 |
Bidding & Construction | 1/2024 | 7/2026 |
Owner Occupancy | 7/2026 | 7/2026 |
Project Budget
Total Budget | Bond Amount | Construction Budget | Owner Costs |
---|---|---|---|
$172,765,706.00 | $156,000,000.00 | $142,752,268.00 | $30,013,438.00 |